In a workspace with a team, some people write posts and others decide what goes out. A post written by someone who can’t publish waits as PENDING_APPROVAL until someone approves it.

How a post comes to wait

A key acts as its person, with their role in the workspace. When that person can’t publish and saves a post with schedule or publish_now, nothing goes out. The post’s status is PENDING_APPROVAL instead. A post sent for approval through the API or MCP goes to every member whose role can approve. On the Free plan it counts toward the 20 posts a month when it’s sent, not again when it’s approved. To find what’s waiting, subscribe a webhook to approval.requested. It carries the post and the actor who sent it. You can also list posts and look for PENDING_APPROVAL.

Approve a post

Approve a post with POST /posts/{id}/approve. The key needs posts:approve, and its person must be allowed to approve that post. type says what happens next:
It answers with the post, now SCHEDULED. schedule_for is read in the workspace’s timezone, unless you add timezone inside it ("schedule_for": { "date": "2030-03-15", "time": "09:00", "timezone": "Europe/London" }). Rows that had failed go back to PENDING, so they go out with the rest. When the post is approved, PostSyncer sends approval.approved. Rejecting a post is done in the app, with a reason for its writer. That sends approval.rejected, with the reason. Webhook events shows what each one carries.
posts:approve lets a key publish a waiting post, even without posts:publish. Give it only to keys you’d trust to publish.

When approving is refused

Edit a waiting post

Leave schedule_type out of an update and the post stays PENDING_APPROVAL, at its time while that time is ahead. Otherwise it takes the next free queue time, or keeps its time (or none) when none is free. That needs posts:schedule. With "schedule_type": "draft", it leaves the approval queue and becomes a draft.

Change an approved, scheduled post

Once a post is SCHEDULED, someone who can’t publish can’t edit it with an update on their own. Their update with schedule_type left out, or with draft, answers 403, and nothing is saved:
To ask for a new approval, send the same change with "schedule_type": "schedule". The post goes back to PENDING_APPROVAL, its approvers are asked again, and PostSyncer sends approval.requested. Leave schedule_for out to keep the post’s time while it’s ahead.
A post that repeats after it went out (PUBLISHED, PARTIALLY_FAILED or FAILED, with repeats ahead) can’t be changed by them with schedule_type left out or draft either. That answers 403 with This post repeats, and its next repeats send what was approved. Ask someone who can publish to change it, or duplicate it and send the copy for approval.

With MCP

approve-post takes the post’s id, type and schedule_for, and needs posts:approve. get-post-history shows who sent and answered it. An agent should ask the user before it approves: approving with publish sends the post. See the MCP tools reference.